    Roadwork in Desert Hot Springs will cause closures. Here's what to know

    By Ani Gasparyan, Palm Springs Desert Sun,

    4 days ago
    https://img.particlenews.com/image.php?url=4JQXuk_0uUpZRBa00

    Desert Hot Springs and Riverside County have started working on repairs to two roads in the northern part of the city, Mission Lakes Boulevard and Little Morongo Road. They will result in some road closures.

    On Tuesday, the city council unanimously authorized a construction agreement with Vance Corporation for a resurfacing project on the two roads. Construction began on July 15 and is estimated to conclude in September, according to the county.

    Riverside County has been working on resurfacing projects in unincorporated areas and awarded a construction agreement to Vance Corporation for the portion of the roads in their jurisdiction. These are general repairs not related to Hilary, a storm in August 2023 that caused serious damage to many roads in the Coachella Valley, including Little Morongo Road.

    Previous coverage:Desert Hot Springs approves over $8 million to repair roads damaged by Hilary

    “The county was actually coming in and doing these street improvements, and we generally will like to maximize the fact that they’re already mobilized and tie in to do our half of the roads,” said Deputy City Manager Doria Wilms.

    Parts of both roads run along a boundary between the city and the unincorporated section that includes Mission Lakes Country Club.

    Where are the repairs taking place?

    The following portions of the roads will be repaired, according to a city staff report:

    • Mission Lakes Boulevard from Clubhouse Blvd to Little Morongo Road.
    • Little Morongo Road from Mission Lakes Blvd to Augusta Avenue.

    The county's transportation website also states that it is resurfacing a 670-foot stretch of Langlois Road running north from Clifton Street, which is several miles east of city limits.

    That's about 10 miles away from the work being done on Little Morongo Road and Mission Lakes Boulevard.

    What do the repairs entail?

    The repairs will include resurfacing and striping the roads, and utility adjustments as-needed.

    What is it costing?

    The city's total budget for resurfacing the two roads is $654,532.59, which includes a 10% contingency and $50,000 for utility adjustments if needed. The city will be paying for the project with funds from Senate Bill 1, a 2017 state transportation funding measure, according to the city staff report.

    The county's total construction cost for its portions of the roads is $2.1 million.

    How will this impact drivers?

    Construction will take place throughout the week and drivers are urged to be cautious in the area.

    Mission Lakes Boulevard, from Warwick Drive and Little Morongo Road, will be closed from July 22 to 28, according to the county. Drivers will still have access to Warwick Drive and Little Morongo Road through a detour. There will also be no parking signs posted, which will have the dates and times for when the restrictions are in place.

    Ani Gasparyan covers the western Coachella Valley cities of Desert Hot Springs and Cathedral City. Reach her at ani.gasparyan@desertsun.com.