Loxahatchee Road Project in Parkland is Now 24% Complete
By Matt Pfingsten,
19 hours ago
PARKLAND, FL- The Loxahatchee Road construction project in Parkland continues to progress steadily. The project, which is expected to take around 3 years from start to finish, is now 24% complete, according to the Florida Department of Transportation.
The following steps of progress were completed in June:
• Contractor completed sheet pile installation at 4 out of 5 locations to the east of SR 817/N University Drive. • Contractor completed interceptor drainage structure and pipe connections at 3 out of 6 locations to the east of SR 817/N University Drive. • Contractor continued with gravity wall installation between Parkside Drive and SR 817/N University Drive, with approximately 30% completed. • Contractor continued with the eastbound SR 817/N University Drive roadway construction to the west of Parkside Drive. • Contractor began roadway widening on the westbound lane between Parkside Drive and SR 817/N University Drive. • FP&L continued with utility relocation efforts and adjustments.
Get updates delivered to you daily. Free and customizable.
Welcome to NewsBreak, an open platform where diverse perspectives converge. Most of our content comes from established publications and journalists, as well as from our extensive network of tens of thousands of creators who contribute to our platform. We empower individuals to share insightful viewpoints through short posts and comments. It’s essential to note our commitment to transparency: our Terms of Use acknowledge that our services may not always be error-free, and our Community Standards emphasize our discretion in enforcing policies. We strive to foster a dynamic environment for free expression and robust discourse through safety guardrails of human and AI moderation. Join us in shaping the news narrative together.
Comments / 0