    A weekly list of highlights from commercial land use review activity in Portland by the Bureau of Development Services in the prior week.

    Type 3 procedure (conditional use) pending

    Address: within the 97231 zip code

    Applicants: Meredith Armstrong and Randy Franks of PGE

    Owner: city of Portland

    Portland General Electric (PGE) is requesting approval to construct a new 1,400-foot-long segment of transmission corridor and shift a portion of existing transmission corridor slightly south to make necessary wire routing improvements. All work in Forest Park is proposed within existing PGE utility easements. For the work to take place, 4.78 acres of forest habitat in the park must be cleared; the land is surrounded by utility corridors on all sides. Work would also occur at PGE’s Harborton Substation at 12500 N.W. Marina Way. Only a negligible amount of new impervious surfaces would be required; clean runoff would enter surrounding forest soils.




    Type 1 procedure (design review) pending

    Address: 1130 N.W. 22nd Ave.

    Applicant: Phillip Kitzes of J5 Infrastructure Partners of Maple Valley, Washington

    Owner: Good Samaritan Hospital Medical Center

    A new wireless facility would be added to the existing building’s rooftop. The equipment would include antennas, radios, GPS, batteries (emergency backup), a cabinet, and other ancillary items necessary for operation. All items would be placed in two areas and screened with fiber-reinforced plastic that would match the building facade’s color and texture.




    Type 2 procedure (adjustment) pending

    Address: 312 N.E. 57th Ave.


    Applicant: Peter Grimm of Scott Edwards Architecture

    Owner: 312 NE 57th Series of the Kent Family Holdings LLC

    The scope includes demolition of three existing structures and construction of a 28-unit apartment building. The proposal calls for the inclusion of a courtyard, a community room, and a tuck-under parking lot.




    Type 1 procedure (design review) pending

    Address: 375 N.E. Holladay St.

    Applicant: Marina Monihan of Technology Associates EC

    Owner: XHR Portland OCC LLC

    Dish Wireless LLC proposes installation of three new antennas and six new radios on the rooftop with fiber-reinforced plastic screening painted to match the structure. One new five-foot-by-seven-foot platform with two cabinets and associated utility equipment will be behind existing building equipment screening.





    Early assistance pending

    Address: 4310 S. Macadam Ave.

    Applicant: Andrew Smith of Hennebery Eddy Architects

    Owner: 4310 Building LLC

    Plans call for adding exterior security enhancements.




    Early assistance pending

    Address: 5615 S. Macadam Ave.

    Applicant: Nathan Arnold of Faster Permits

    Owner: Lindquist Development

    Plans call for converting an existing bank building into a McDonald’s restaurant. The driveway would be reconfigured to accommodate dual lane order points and a new trash corral. Parking would change as necessary. Stormwater would be handled on-site in a retention basin.





    Type 1 procedure (design review) pending

    Address: 123 N.W. 12th Ave.

    Applicant: Sarah Skreen of Technology Associates EC (on behalf of T-Mobile USA)

    Owner: not listed

    The proposal calls for installation of six antennas wrapped in stealth material, one 10-foot-by-15-foot equipment platform, two cabinets, and more on the rooftop.




    Source: Portland Bureau of Development Services