    Highway 395 improvements bring road closures, slowdowns through December

    By Rene Ray De La Cruz, Victorville Daily Press,

    8 hours ago

    A road improvement project scheduled through December will affect traffic at various locations along Highway 395 in the High Desert.

    Commuters will notice the beginning of slowdowns and road closures from Monday, Oct. 7 to Thursday, Oct. 17 on Highway 395 as crews continue to work in Adelanto, Hesperia, and Victorville.

    https://img.particlenews.com/image.php?url=0TR7xB_0vx4w2ot00

    Some projects include pavement upgrades, installing changeable message signs and upgrading facilities to meet Americans with Disabilities Act standards.

    The project, designed to refurbish existing roads, and enhance safety, and accessibility, is part of the $43 million roadway improvement project funded through Senate Bill 1, the Road Repair and Accountability Act of 2017.

    Highway 395 work schedule, closures

    From Monday to Thursday, night work continues from 10 p.m. to 6 a.m.

    On Sunday, Oct. 13, night work will last from 10 p.m. to 6 a.m. through Thur. Oct. 17.

    Work will occur in Hesperia, between Joshua Street and Palmdale Road on Route Highway 395 and move northbound.

    Motorists should expect nighttime lane closures with reverse traffic control at various areas on the route that may also require alternating lane closures.

    Interstate 15 connector closures are taking place at night at the following locations:

    • Northbound I-15 to NB Highway 395
    • Southbound Highway 395 to SB I-15

    A pilot car will escort motorists through the construction zone areas. Commuters should expect potential traffic delays with reverse lane and shoulder closures, alternating between both northbound and southbound directions.

    Road users are reminded to reduce speed in the work zone and to be mindful the weather and other factors may affect the construction schedule.

    https://img.particlenews.com/image.php?url=0Xj1oL_0vx4w2ot00

    Road project funding, resources

    Senate Bill 1 provides $5 billion in transportation funding annually split between the state and local agencies.

    Road projects progress through construction phases more quickly based on the availability of SB 1 funds, including projects that are partially funded by SB 1.

    For more information about transportation projects funded by SB 1, visit RebuildingCA.ca.gov .

    Visit the Caltrans District 8's Facebook and Twitter accounts or the agency's website for additional updated information.

    Motorists can plan commutes and view live traffic conditions and planned lane closures by using Caltrans' QuickMap.

    For those with sensory disabilities and those needing information in a language other than English, contact Public Affairs at 909-383-4631 or TTY 711.

    This article originally appeared on Victorville Daily Press: Highway 395 improvements bring road closures, slowdowns through December

    Expand All
    Comments / 1
    Add a Comment
    ULTRA_MAGA1776
    5h ago
    Make it bigger…
    View all comments
    YOU MAY ALSO LIKE
    Local News newsLocal News
    The Shenandoah (PA) Sentinel20 days ago
    Robert Russell Shaneyfelt28 days ago
    Robert Russell Shaneyfelt21 days ago
    Robert Russell Shaneyfelt1 day ago

    Comments / 0