    ODOT Weekly Construction Update

    3 days ago

    https://img.particlenews.com/image.php?url=3ei5oX_0uWgAs0J00

    The following construction projects are anticipated to affect highways in Pike County next week. All outlined work is weather permitting. Projects with active or future traffic impacts are linked to OHGO.com.

    NEW

    State Route 335 Slide Repair

    Work is set to begin on July 15 for a slide repair project between Schilder Lane and Omega. Work will occur daily for this construction. S.R. 335 will be closed for the duration of the project; traffic will be detoured via S.R. 220 to S.R. 32.

    Estimated completion: August 23, 2024

    U.S. 23 Resurfacing

    Work has begun as of July 1 for a resurfacing project on U.S. 23 between the City of Waverly and the Ross County line. Work will occur daily for this construction. At least on lane will be maintained for the duration of the project.

    Estimated completion: Summer 2024

    ONGOING

    County Road 8 Bridge Replacement

    Work has begun as of May 8 for a bridge replacement project on C.R. 8 (Dry Bone Road) between S.R. 41 and Fairview Road. Work will occur daily for this construction. Dry Bone Road will be closed for the duration of the project; traffic will be detoured via Fairview Road to Lapperell Road to S.R. 41.

    Estimated completion: Summer 2024

    State Route 32 Resurfacing

    Work has begun as of May 6 for a resurfacing project on S.R. 32 between the Adams County line and Goff Road and between Beaver Creek Road and Tennyson Road. At least on lane will be maintained for the duration of the project.

    Estimated completion: Summer 2024

    State Route 104 Bridge Replacement

    Work has begun as of February 26 for a bridge replacement project on S.R. 104 between S.R. 32 and Long Fork Road. S.R. 104 will remain open until July 8.

    Beginning July 8, S.R. 104 and access to Long Fork Road from S.R. 104 will be closed all directions for approximately 2 weeks.

    Traffic will be detoured via S.R. 32 to U.S. 23 to S.R. 348.

    Following the 2-week closure, the Southbound lane of S.R. 104 will be open from S.R. 32.

    Estimated completion: Fall 2024

    Super Load

    A Super Load is expected to impact various roadways in Pike County. To sign up for route information and updates, visit transportation.ohio.gov/superload